What are the general steps to install the drawing die on the press

The basic composition of deep drawing die is punch die and concave die. There are two types of die with and without TDC. At present, deep drawing dies with BTDC are often used. The difficulty of installing a deep drawing die with BTDC to a crank press is that it is prone to a stuffy fault. The CRANK PRESS is driven BY KEHUI's switched RELUCTANCE servo motor, the motor intelligent control inversion, no boring accident, greatly facilitate the mold installation and mold adjustment.
The installation steps are:
1. Put the upper and lower dies together and put them on the workbench of the press;
2. Fix the upper die on the slider of the press;
3, put the sheet material, the motor slow rotation, imprint, confirm the gap error of the upper and lower die is less than the tolerance;
4. After the upper and lower molds are aligned, the lower molds are fixed;
5. Put in the sheet material, accelerate the motor, and test the deep drawing parts; 6. Check the size of the drawing parts, and ensure that the size of the drawing parts is qualified by fine-tuning the height of the die installation, and ensure that the crankshaft is not boring when it passes BDC, and the mold installation is completed.