The process of mold assembly

 

(1) Before the final assembly should select the assembly of the benchmark, arrange the upper and lower die (dynamic, fixed die) assembly sequence. If the guide plate is used as the reference for assembly, the punch shall be mounted to the fixed plate through the guide plate, and then the lower die shall be mounted through the upper die. In the final assembly, when the mold parts into the upper and lower templates, first installed as the reference parts, check and then tighten the screw, drive into the pin. Other parts shall be installed with reference parts, but do not tighten screws. Tighten them after the clearance is adjusted and the test punch is qualified.


(2) Cavity die usually takes the main parts to be hardened (such as the moving die) as the benchmark, and then processes the other parts associated with them respectively after all machining. Then processing fixed die and fixed plate 4 guide hole, combined slider, guide rail and core parts, boring oblique guide hole, install the top rod and roof. Finally, the moving template, pad, pad, fixed plate and so on.

 

Send Inquiry